04 Apr 2022 Hauraki District Bridge Repairs
Posted in Bridges, Case Studies, Concrete Repairs, Epoxy Injection
Client: Hauraki District Council
Engineer: WSP Hamilton
This project comprised the structural repair to eight bridges and culverts distributed over the Hauraki District as part of the repair programme for 2021/22.
The scope of work varied by structure:
- Crack injection to bridge hollowcore units
- Concrete repairs including major breakout and replacement of a bridge pier element and spall repairs
- Culvert invert repairs and watercourse clearing
- Kerb block replacement (precast and insitu)
- Bearing and joint replacement
- Minor steelwork repairs
The commencement of the work was significantly disrupted by Covid lockdowns but once this was cleared the team got stuck in and completed the work in a prompt and timely manner.